JVC handover tracker

Off-plan projects past their registered end date.

64Projects on the register
16,228Homes in them
27 of 34Due so far and late
52%Median complete, late ones

The Land Department register lists 64 JVC projects with 16,228 homes. Of the 34 due before 11 Oct 2026, 7 were finished and 27 were late, at a median 52% complete and 3.4 months past the date.

ProjectRegister end dateCompleteInspectedMonths past
Binghatti Ruby28 Feb 2026 46%20 Jul 20267
Binghatti Amberhall28 Feb 2026 38%12 Jan 20267
Lodge Residences by Riviera Azure1 Mar 2026 63%13 Jul 20267
Samana Waves 220 Mar 2026 52%24 Sep 20267
Roma Residences by JRP31 Mar 2026 77%15 Sep 20266
Palatium Residences31 Mar 2026 88%14 Sep 20266
Almaan 10113 Apr 2026 51%11 Mar 20266
Elysee Heights14 Apr 2026 81%18 May 20266
Samana Waves15 Apr 2026 90%13 May 20266
Parkwood Residences30 Apr 2026 57%14 Sep 20265
Waref Residences by Sido Development1 May 2026 81%8 Apr 20265
Skyhills II by HRE1 Jun 2026 95%20 Jul 20264
Violet Tower30 Jun 2026 70%3 Jun 20263
Lucky Oasis Residence30 Jun 2026 20%30 Apr 20263
Casa Vista Residence by Golden Woods30 Jun 2026 90%3 Jun 20263
The Fifth Tower24 Jul 2026 50%22 Jul 20263
Aveline Residences by Citi Developers26 Jul 2026 42%11 Jun 20262
The Orchard Place31 Jul 2026 43%31 Mar 20262
Rose Gardens 230 Aug 2026 32%2 Jun 20261
Belle Reve by Zimaya31 Aug 2026 80%7 Sep 20261
Sereno Residences1 Sep 2026 22%29 Jul 20261
77 Boulevard by Bam10 Sep 2026 18%16 Mar 20261
Havelock Heights15 Sep 2026 28%17 Jun 20261
Exotica by Al Marina30 Sep 2026 41%15 May 20260
Vue by Crystal Bay1 Oct 2026 68%20 Aug 20260
Eco Harmony Tower1 Oct 2026––0
Hearth Heights by ENAWT Real Estate Development1 Oct 2026 29%24 Jun 20260

Dubai Land Department project register, read 11 Oct 2026. It shows the current end date, not the first promised date.