JVC handover delays by developer

Projects past their registered end date, grouped by developer.

21 of 24Developers with late projects
27Late projects
3.4Median months late

21 of 24 developers with JVC projects due by 11 Oct 2026 have at least one past its end date. Median delay 3.4 months.

By developer

DeveloperDueLateMedian % done
Binghatti4242.2%
Samana2271.1%
Object One1150.3%
HRE2195%
Pantheon1181.2%
Lucky Aeon1120%
Citi1142.2%
Peak Summit1142.7%
Dubai Investment Real Estate1170.4%
Riviera Azure1163.3%
Zimaya1180.5%
Arabian Gulf1157%
Crystal Bay1168.2%
Ahmadyar1187.9%
AA and HMB1128.0%
Sido1181.1%
JRP1176.8%
Svarn1122.4%
Casa Vista & Golden Woods1190.0%
Al Marina Investment1141.1%
MN Vision1150.9%
Imtiaz10–
Taraf10–
Heilbronn10–

Dubai Land Department project register, read 9 Oct 2026.

Next step

Want to view JVC off-plan homes? Leave your WhatsApp

We use your number only to send you these updates. One message a month at most. Reply STOP to end it. Privacy.

Related

Questions

Which JVC developer has the most late projects?

Binghatti: 2 late of 4 due.

How late are JVC projects?

Median 3.4 months past the end date, 51.5% complete.

Dubai Land Department project register, read 9 Oct 2026.

Data to: sale figures 5 Nov 2026 (cube) · latest sales 11 Nov 2026 (register) · signed rents 11 Nov 2026 · what changed
DaliaAIAsk DaliaAI analyst