How many JVC off-plan projects are late?
Answered from the records, data to 11 Oct 2026.
Of the 34 JVC projects due before 11 Oct 2026 on the Land Department register, 27 were past their end date, at a median 52% complete and 3.4 months late.
Source: Dubai Land Department project register, read 11 Oct 2026. Data to 11 Oct 2026.